Risk Management in Loan Programming of Public Works Infrastructure Construction (Lesson Learned of Indonesia Tourism Development Project)
DOI:
https://doi.org/10.59141/jiss.v7i5.2338Keywords:
risk management, last planner system, loan programAbstract
Loan programs serve as an alternative funding source for public infrastructure development in Indonesia, yet they often face significant delays due to complex organizational structures, readiness criteria, procurement procedures, and technical challenges. This study aims to formulate risk management recommendations for loan-funded public works infrastructure projects by drawing lessons from the Indonesia Tourism Development Project (ITDP), implemented from 2018–2024. The research adopts a qualitative case study approach using the Last Planner System (LPS) framework, which includes Master Schedule, Phase Planning, Modified Lookahead Planning, and Weekly Work Planning. Data were collected from CPMU, PMU, and PIU progress reports, operational manuals, audit records, and lender evaluation documents. The findings reveal that combining planning and construction within the same loan period is a primary source of delay, as the formulation of the Integrated Tourism Master Plan consumed nearly half of the project timeline. Other critical issues include land availability, procurement document mismatches, technical adjustments during construction, and institutional gaps in asset handover to local governments. The study concludes that loan programs should separate planning from construction phases, prioritize subprojects based on societal impact, ensure readiness criteria are fulfilled before commencement, and establish early stakeholder collaboration. These LPS-based recommendations provide a structured approach for future loan managers to anticipate and mitigate implementation delays.
References
Amoah, K. B. O., El-Asmar, M., & Chalker, M. (2024). Influence of BIM and lean on mitigating delay factors in building projects. Results in Engineering, 22, 102093. https://doi.org/10.1016/j.rineng.2024.102093
Amoah, K. B. O., Okere, G., & Deshpande, A. (2024). Construction delay analysis: Causes, impacts, and mitigation strategies. Journal of Civil Engineering Research, 14(1), 1–9. https://doi.org/10.5923/j.jce.20241401.01
Buitrago-Mora, J., Palacios-Manzano, M., & León-Gómez, A. (2024). Bridging the gap: Mobilization of multilateral development banks in infrastructure. World Development, 176, 106524. https://doi.org/10.1016/j.worlddev.2023.106524
Clarke, V., & Braun, V. (2022). Thematic analysis: A practical guide. SAGE Publications.
Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications.
Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners’ perspective of factors contributing to project delay: Case studies of road and bridge projects in Saudi Arabia. Procedia Engineering, 145, 1402–1409. https://doi.org/10.1016/j.proeng.2016.04.176
Ferreira, D., Khatua, M., Agha, S., & Suárez-Alemán, A. (2023). Bridging the gap: Mobilization of multilateral development banks in infrastructure. World Development, 173, 106401. https://doi.org/10.1016/j.worlddev.2023.106401
Hamzeh, F. R., El Samad, G., & Emdanat, S. (2019). Advanced metrics for construction planning. Journal of Construction Engineering and Management, 145(11), 04019065. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001699
Kim, K. (2023). Analysing Indonesia’s infrastructure deficits from a developmentalist perspective. Competition & Change, 27(1), 3–24. https://doi.org/10.1177/10245294211043355
Lapinski, A. R., Horman, M. J., & Riley, D. R. (2006). Lean processes for sustainable project delivery. Journal of Construction Engineering and Management, 132(10), 1083–1091. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:10(1083)
Lapinski, A. R., Horman, M. J., & Riley, D. R. (2021). Lean processes for sustainable project delivery. Journal of Construction Engineering and Management, 147(5), 04021023. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001986
Omotayo, T. S., Ross, J., Oyetunji, A., & Udeaja, C. (2024). Systems thinking interplay between project complexities, stakeholder engagement, and social dynamics roles in influencing construction project outcomes. SAGE Open, 14(2). https://doi.org/10.1177/21582440241255872
Orya, F., & Calahorra-Jiménez, M. (2025). Delays in infrastructure projects: Main reasons in the design, procurement, and construction phases. Public Works Management & Policy, 30(1), 1–28. https://doi.org/10.1177/1087724X241308310
Osei-Kyei, R., & Chan, A. P. C. (2023). Construction risk management research: Intellectual structure and emerging themes. Engineering, Construction and Architectural Management, 30(2), 521–546. https://doi.org/10.1080/15623599.2023.2167303
Power, W., Sinnott, D., & Lynch, P. (2024). Synthesizing Last Planner® System, Takt, and Scrum theory and practice to enhance construction project delivery. Lean Construction Journal, 2024, 16–28. https://doi.org/10.60164/3xymkr1ws
Quiroz, J., Arce, J., & Ramirez, M. (2023). Implementation of lean management and delay analysis in a utility power distribution project. Proceedings of the 1st International Conference on Recent Advancements in Infrastructure Developments (RAID). National Institute of Technology, Kozhikode.
Quiroz, L., Torres, J., & Alcántara, G. (2023). Application of lean construction and Last Planner System in tracks-and-greenways infrastructure project in Lima. SSRG International Journal of Civil Engineering, 10(4), 28–37. https://doi.org/10.14445/23488352/IJCE-V10I4P104
Sadick, A. M., & Issa, M. H. (2024). Systematic review on stakeholder collaboration for a circular built environment: Current research trends, gaps and future directions. International Journal of Project Management, 42(3), 102585. https://doi.org/10.1016/j.ijproman.2024.102585
Tor, M. A., & Gambo, N. (2024). Impact of stakeholders’ engagement on construction projects: A case study of Katsina Central Market. International Journal of Project Management, 6(4), 1–17. https://doi.org/10.47672/ijpm.2420
Yin, R. K. (2018). Case study research and applications: Design and methods (6th ed.). SAGE Publications.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Aryawidia Pariantho

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International. that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.